Expected Gas Sourcing

LNG ()

Comments about the Third-Party Access Regime

Issues regarding the TPA regime will be determined at the later stages of the Project implementation

Benefits

Main Driver

Regulation SoS

Main Driver Explanation

Benefit Description

The project should create conditions for natural gas reserve storage in Lithuania, increase the security of supply in the region (Latvia and by using

Lithuanian-Polish gas internconnection (GIPL))and contribute to the creation of national as well as regional gas market, increase the flexibility of the whole

sytem.

Technical Information (UGS)

Storage Facility

Syderiai underground gas

storage

Storage Facility Type

Aquifer

Multiple-Cycle

No

Working Volume (mcm)

500.00

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

Commissioning

2019

2019

NDP and PCI Information

Part of NDP

No (NPD was prepared by public entities,

which didnt include projects form third

parties. Yet project is included in the

National energy independancy strategy.)

NDP Number

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

No

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 389 of 620

Current TYNDP : TYNDP 2017 - Annex A