Gas Interconnection Poland-Lithuania (GIPL) (Lithuania's section)

General Information

Promoter

AB Amber Grid

Operator

AB Amber Grid

Host Country

Lithuania

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

AB Amber Grid

100%

TRA-N-341

Project

Pipeline including CS

Non-FID

Update Date

06/05/2016

Advanced

Description

The project is aimed to establish a well-functioning new bidirectional interconnection between the Polish and Lithuanian gas transmission systems to

integrate the isolated gas markets of the Baltic States into the EU gas grid, by introducing an alternative gas supply route to the Baltic States. By

implementing the project a 165 km-long and 700 mm-diameter pipeline and gas pressure reduction and metering station will be constructed on

Lithuania's side.

Regulatory Decisions and

similar material conditions

On 11 August 2014 ACER adopted a decision No 01/2014 On The Investment Request including Cross-Border Cost Allocation for The Gas

Interconncetion Poland-Lithuania Project of Common Interest No. 8.5.

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Interconnector PL-LT

AB Amber Grid

2019

LT

PL

51.1 GWh/d

AB Amber Grid

2019

PL

LT

73.9 GWh/d