Bordolano Second phase
General Information
Promoter
STOGIT S.p.A.
Operator
STOGIT
Host Country
Italy
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
UGS-F-1045
Project
Storage Facility
FID
Update Date
13/06/2016
Advanced
Description
The project is related to the conversion of the depleted reservoir of Bordolano, into a reservoir for the storage of methane gas
Regulatory Decisions and
similar material conditions
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
UGS - IT - Snam Rete Gas/STOGIT
STOGIT
2019
STcIT
IT
185.0 GWh/d
Comment: Interconnection point Storage hub/Transportation grid is a commercial point. The
capacity available is equal to the capacity offered or planned to be offered by the storage
companies.
STOGIT
2019
IT
STcIT
109.0 GWh/d
Comment: Interconnection point Storage hub/Transportation grid is a commercial point. The
capacity available is equal to the capacity offered or planned to be offered by the storage
companies.
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 386 of 620
Current TYNDP : TYNDP 2017 - Annex A