Local Fuel PLC – The Shoreham Oil Terminal

Safety Instrument System Overfill Shutdown Conditions Proof Testing Procedure LFS-SIS1

P & I Design Ltd

DOCUMENT NO: LF364012_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 20.05.15

Tel: + 44 (0)1642 617444

PAGE 20 OF 22

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

Step

Method of Test

Acceptance Criteria

Pass (

)

Fail (x)

Initial

10.1.5

Operate and release HS Test Switch

The sensing element will initiate a test

sequence on rising edge of test switch.

Test sequence =

5 seconds self-test

2 seconds alarm condition

Returns to healthy state

Valve action found smooth with full

operation of valve stem.

Comment poor action / sticking in

section 10.1.7.

Valve status ESD Tripped on Local

display.

Comment failure in section 10.1.7.

System trips closing and inhibiting from

reopening FINAL ELEMENT valves

and initiating DIAGNOSTICS as

detailed on LF364003_SCH Sheet 2&3.

Comment differences from SCH in

section 10.1.7

XV Closing times for overfill and surge

protection with set limits as detailed on

LF364003_SCH Sheet 2.

Comment failures in section 10.1.7.

Record Physical Closing Time and

Physical Travel Time.

10.1.6

Activate system associated Bund reset

and confirm valves enabled by opening

and closing.

System reset as detailed on

LF364003_SCH Sheet 1.

Comment differences from SCH in

section 10.1.7.

10.1.7

Comments/Defects/ Remedial Actions

– Report ALL to System Keeper

Tested by

Position

Qualification

Sign

Date

System Keeper Acknowledgement

(Note: Signature confirms System keeper is advised of Comments/Defects/Remedial Actions and will initiate

terminal procedures for rectification works and/or isolation of plant as required)

Accepted by

Position

Qualification

Sign

Date