Local Fuel PLC – The Shoreham Oil Terminal

Safety Instrument System Overfill Shutdown Conditions Proof Testing Procedure LFS-SIS1

P & I Design Ltd

DOCUMENT NO: LF364012_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 20.05.15

Tel: + 44 (0)1642 617444

PAGE 19 OF 22

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

10

AS LEFT FUNCTIONAL PROOF TESTING PROCEDURE

10.1 Drexelbrook Sensor As left Manufacturers Test Terminal Functional Testing

Purpose of Test

To verify the SIF operates correctly following system disturbance.

SIF is SENSOR ELEMENT trips & inhibits the FINAL ELEMENT(s) to the safe state as specified.

Method of activation is by operation of the manufacturers test facility

To verify the correct DIAGNOSTICS information.

If sensing element defective the tank could overfill if a demand is made on the overfill protection

system.

If response target time is exceeded the tank could overfill following demand.

Diagnostic information not displayed correctly could result in undetected tank overfill, system

unavailability or incorrect operational response.

Controlled Copy Documentation Required

LF364003_SCH - LFS-SIS1 Testing Matrix.

Record results on LF364003_SCH Sheet 3.

Step

Method of Test

Acceptance Criteria

Pass (

)

Fail (x)

Initial

10.1.1

Review procedure with operations and

testing personnel.

All personnel familiarised with the

scope of works and responsibilities

.

Comment any issues in section 10.1.7

and review / rectify prior to starting test.

10.1.2

Confirm plant preparations satisfactory

prior to each period of work and

following changes in plant conditions

or operations.

Record PTW No………………………….

Conditions satisfied as detailed on PTW

and RAMS.

Comment any issues in section 10.1.7

and review / rectify prior to starting any

site work.

10.1.3

Confirm system healthy and reset by

comparing against information on

LF364003_SCH Sheet 1.

System reset as detailed on

LF364003_SCH Sheet 1.

Comment differences from SCH or if

found in tripped state in section 10.1.7.

10.1.4

Confirm all final element valves

tripped by the initiator under test are

open.

Correct FINAL ELEMENT valve

position and DIAGNOSTICS as detailed

on LF364003_SCH Sheet 2.

Comment differences from SCH in

section 10.1.7.

Drexelbrook Sensor As left Manufactures Test Terminal Functional Testing Continued on page 20