24 |
ENTSOG – GRIP Central Eastern Europe 2014–2023
PCI – LNG
Non-PCI – LNG
PCI – Transmission
Non-PCI – Transmission
PCI – UGS
Non-PCI – UGS
13
26
88
88
7
37
Projects
Figure 2.1:
Breakdown of the projects in TYNDP 2015 per PCI status (as approved in 2013) and
per type of infrastructure
LNG Terminal – FID
LNG Terminal – Non-FID
UGS – FID
UGS – Non-FID
Transmission – FID
Transmission – Non-FID
2013
2015
7
32
29
151
25
15
10
35
14
27
49
145
6
9
%
1
5
%
1
6
%
6
8
%
1
7
%
1
5
%
Projects
Projects
Figure 2.2:
Comparison of project submission in TYNDP 2015 and TYNDP 2013 per type of
infrastructure and FID status. The outer circle represents absolute numbers;
the inner circle represents the share of each project type.
Table 2.1:
Breakdown of projects in TYNDP 2015 by FID status and PCI status
For each project, the commissioning year is related to the first capacity increment of
the project in the case where there is more than one increment. For projects where
the commissioning date is not available (N/A) in the Annex A, it means that the
promoter has not submitted a capacity increment or did not specify a year within the
time horizon. The first full year of operation used in the assessment is the first full
calendar year following the commissioning date.
The following figures provide a statistical overview of the projects (see Annex A
for project details) based on information such as the type of infrastructure or the
FID/PCI status.
BREAKDOWN OF PROJECTS IN TYNDP 2015
BY FID STATUS AND PCI STATUS
PCI
Non-PCI
TOTAL
FID
13
34
47
NON-FID
95
117
212
TOTAL
108
151
259
The number of projects submitted for inclusion in the TYNDP remains high showing
the need to expand market integration benefits to the whole of Europe.