Old FID: projects already FID in TYNDP 2013
New FID: FID project in TYNDP 2015,
included as Non-FID in TYDNP 2013
Old Non-FID: projects still Non-FID in TYNDP 2015
New Non-FID: project Non-FID in TYNDP 2015,
included as FID in TYNDP 2013
%
18
6
76
1
Figure 2.8:
FID status in TYNDP 2015 for the 181 projects submitted to both TYNDP 2013
and 2015
Projects in delay
Projects not in delay
Total: 86
57
39
Figure 2.9:
Share of projects reporting their expected FID date in both TYNDP 2013 and 2015
Projects in delay
Projects not in delay
Projects according to
original schedule
Total: 71
29
17
25
Figure 2.10:
Share of projects reporting their expected construction start date in both
TYNDP 2013 and 2015
Out of the 259 projects included in TYNDP 2015, 181 were already part of
TYNDP 2013. The following chart illustrates the FID status of those common projects
according to TYNDP 2015 submission:
Out of those common projects, 86 have reported in both TYNDPs when they plan to
take their FID. The following chart illustrates the share of these 86 projects whether
they have reported some delay in their expected FID date:
Out of those common projects, only 71 projects have reported when they plan to
start construction. The following chart compares for these 71 projects the evolution
of the estimated construction start date between TYNDPs 2013 and 2015:
This overview of project progression from one edition to the other shows promoter
commitment to commission on time once FID has been taken. The current econom-
ic and legislative environment seems to have prevented many promoters from taking
their FID within their original expected timeframe.