Background Image
Table of Contents Table of Contents
Previous Page  31 / 232 Next Page
Information
Show Menu
Previous Page 31 / 232 Next Page
Page Background

Ten Year Network Development Plan 2015 |

31

Rate of Return

Low price

of short term capacity

Capacity quotas

Lack of proper

transposition of

EU regulations

Other

%

22

4

3

5

66

Figure 3.3:

Overview of Regulatory related project barriers

3.3.1 REGULATORY FRAMEWORK

For many projects the regulatory framework is perceived as not being appropriate to

ensure the delivery of new infrastructures even when they have been identified as

necessary to complete the integration of the European gas market. The following

graph shows in more detail the regulatory challenges faced by promoters according

to their project submission. The category “Other” covers promoters responses where

a specific category of barrier was not provided and the comments did not allow it to

be further categorized

1)

.

The level of rate of return is perceived as a major

obstacle. Setting the level is exclusively subject to the

national regulatory regimes but should encourage

long-term investments with a reasonable rate of return.

If the rate is too low or not sufficiently stable, then in-

vestments will be put at risk and consequently the

completion of the internal gas market. The setting of

the rate should strike the right balance between the

benefits of further market integration and the impact

on transmission tariffs which represent a moderate

share of the wholesale market price of gas.

The practice of applying incentives, such as premium

rates of return for higher risk projects, has already

been adopted by some Member States.

As part of the Framework Guidelines and Network

Code processes on Capacity Allocation Mechanism

and Harmonised Transmission Tariff Structures for

Gas, NRAs have followed the request of some market players in favouring low priced

short term capacity products and quotas. In addition to revenue recovery issues,

which such mechanisms could induce, they are inadequate for triggering new in-

vestments.

In addition, within the development process of the draft Tariff Network Code some

network users have claimed the right to cancel all or part of their capacity bookings

linked to tariff changes. If such situation would emerge, this will lead to cross-subsi-

dies between network users as a result of revenue neutrality for the operators

furthermore the value of any long term commitment would be weakened. This would

be major risk for investment realization.

The TEN-E Regulation was designed to support the delivery of key infrastructure

projects necessary to the completion of the Integrated Energy Market. Many network

users presume that associated EU financing will reduce their need of financial com-

mitment. Such expectation could result in an even lower willingness of the market

to commit in new infrastructures. In parallel, the cross-border cost allocation, which

was anticipated as new tool to foster investment decision, now appears to many pro-

moters as a source of delay and uncertainty.

The second selection of PCIs should address some concerns regarding the efficien-

cy of the selection process and could also help to identify good practices in terms of

permitting and regulatory incentives. Such mechanisms should then be extended to

all projects to help the market to deliver the required infrastructure projects.

Feedback from some project promoters suggests that the TEN-E Regulation, Gas

Target Model discussions and recent emphasis on Security of Supply seem to have

shifted the focus away from the full implementation of the Third Energy Package and

market-based solution across Europe. As identified by promoters, the resulting lack

of implementation in some parts of Europe is an obstacle to new investment deci-

sions.

1) Further explanation can be found in Annex A