Ten Year Network Development Plan 2015 

Table 3.1:

Categories of barriers to investment

Financing

Market

Permit Granting

Regulatory

Political

Other

%

11

26

36

13

9

5

Figure 3.1:

Combined overview of project barriers, as submitted by the promoters

%

13

25

9

32

18

4

%

10

10

27

36

7

%

19

23

5

44

5

5

5

Financing

Market

Permit Granting

Regulatory

Political

Other

LNG

TRA

UGS

Figure 3.2:

Overview of project barriers by project type, as submitted by the promoters (LNG – TRA – UGS)

REGULATORY

Rate of Return

Low price of short term capacity

Capacity quotas

Lack of proper transposition of EU regulations

Other

MARKET

Lack of market support

Lack of market maturity

Other

PERMIT GRANTING

FINANCING

Availability of funds

Amortization rates

Other

POLITICAL

OTHER

The following graph presents the breakdown of the barriers.

The most largely reported barriers originate from the regulatory and market

frameworks. The next graphs show that the predominance of those two barriers is

common to all types of infrastructures: