Local Fuel plc - Shoreham Oil Terminal
Safety Instrument System Functional Safety Assessment Stage 5
P & I Design Ltd
DOCUMENT NO: LF364100_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: A DATE: 15.06.2015
Tel: + 44 (0)1642 617444
PAGE 18 OF 32
Fax: + 44 (0)1642 616447
www.pidesign.co.uko
Section 4.6 details the individual tank activation point for all tanks with the
exception of tanks 11, 18, 18A, 21 & 22 were it states 95% (TBC).
Action 6:
The title of the SRS and other lifecycle documentation is confusing as it is specific
in stating Gasoline Import Safety Instrumented System yet the documents are
written for all tanks not just gasoline. The SRS also provides for future individual
tankside valves. This obviously derives from the previous owner with future plans to
provide individual tank isolation in addition to or opposed to common pipeline
isolation.
Action 7:
Section 4.6.12 – there is a typo error should be Tank 18 not Tank 11 as described in
the Service section.