Figure 38 overleaf breaks down the total forecast expenditure of £17.6 billion by Work Breakdown Structure

component proportion for different project types:

All UKCS projects

Subsea projects

Platform removal projects

FPSO vessel projects

29

It is important to note that the graphs only include the breakdown of expenditure that falls within 2016 to 2025.

Decommissioning projects can span many years and therefore some expenditure associated with a project may

fall outside the survey timeframe.

There are 13 FPSOs forecast to be decommissioned on the UKCS over the next decade, 12 of which are located in

the central North Sea. Decommissioning a field serviced by an FPSO primarily involves subsea activity, although

some expenditure is also associated with disconnecting the FPSO. Following disconnection, FPSOs are typically

relocated or sold for reuse or recycling. These activities are reflected in the breakdown of expenditure seen in

Figure 38. The total forecast decommissioning expenditure for fields serviced by an FPSO is £2.6 billion.

29

Total expenditure for platform removal projects, FPSO projects and subsea projects is £17.3 billion. This does not equal

total forecast expenditure because some projects do not fall clearly into one category and therefore have not been

used to calculate the Work Breakdown Structure percentage for individual project types.