Interconnection Croatia-Bosnia and Herzegovina (west)
General Information
Promoter
Plinacro Ltd
Operator
Plinacro Ltd
Host Country
Croatia
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Sponsors
Croatian part
Plinacro d.o.o.
100%
part in B&H
BH Gas
100%
TRA-N-303
Project
Pipeline including CS
Non-FID
Update Date
13/07/2016
Non-Advanced
Description
Interconnection Croatia-Bosnia and Herzegovina on route Licka Jesenica-Rakovica in Croatia to border with Bosnia and Herzegovina. Bosnian part is
from Trzac to Bosanska Krupa with branches to Bihać and Velika Kladusa.
Regulatory Decisions and
similar material conditions
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Rakovica (HR) / Trzac (BA)
Plinacro Ltd
2026
BA
HR
81.0 GWh/d
Plinacro Ltd
2026
HR
BA
81.0 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 292 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |