LNG terminal Krk
LNG-N-082
Project
LNG Terminal
Non-FID
Update Date
23/05/2016
Advanced
Description
The import terminal for the liquefied natural gas (LNG) will be situated in Omišalj on the Island of Krk, Republic of Croatia. The project is planned as
a stage development: with: 1st stage - FSRU with annual send-out capacity of 1- 4 bcm/y (according to FSRU ship and pipeline availability), 2nd
stage - LNG onshore terminal with annual send-out capacity of 3.5 bcm/y, 3rd stage - LNG onshore terminal with annual send-out capacity of 5
bcm/y and 4th stage - LNG onshore terminal with annual send-out capacity of 8.75 bcm/y. Construction and the size of the onshore terminal will
depend on the market need. Future LNG Terminal will be an important part for the security of supply for Central and South-Eastern European
countries. Gas supply in the region is heavily dependent on one supply source and therefore LNG terminal in Croatia would represent a major
diversification gas supply route in the region.
Regulatory Decisions and
similar material conditions
Croatian Energy Regulatory Agency has given to LNG Croatia LLC on 03.02.2016, a permit for performing energy activities which enables LNG Croatia
LLC to operate the terminal.
Capacity Increments Variant For Modelling
Variant : 1. - FSRU
1st phase - FSRU with annual send-out capacity of 1- 4 bcm/y (according to FSRU ship and
pipeline availability)
Point
Operator
Year
From Gas System To Gas System Capacity
Croatia LNG
LNG Hrvatska d.o.o.
2018
LNG_Tk_HR
HR
107.0 GWh/d
Comment: Short-term rented FSRU (min 3, max 5 years)
Commissioning (COD) year - 2018
(Challenging pipeline availability)
Send-out - 1-4 bcm/y
(According to FSRU ship and pipeline availability)
Capacity Increments Variant(s) For Information Only
Variant : 2. - Onshore LNG terminal
2nd phase - LNG onshore terminal with annual send-out capacity of 3.5 bcm/y
Point
Operator
Year
From Gas System To Gas System Capacity
Croatia LNG
LNG Hrvatska d.o.o.
2021
LNG_Tk_HR
HR
-13.0 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 278 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
87