General Information
Promoter
LNG Hrvatska d.o.o. za
poslovanje ukapljenim
prirodnim plinom
Operator
LNG Hrvatska d.o.o.
Host Country
Croatia
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Sponsors
HEP d.d.
50%
Plinacro d.o.o.
50%
Technical Information (LNG)
LNG Facility
The import terminal for
the liquefied natural gas
(LNG) on the Island of Krk
Expected Volume (bcm/y)
4
1st stage - 1-4 bcm/y (According to FSRU ship and pepeline availability), 2nd stage - 3,5 bcm/y, 3rd stage - 5bcm/y, 4th
stage - 8.75 bcm/y
Storage Capacity (m3)
300,000
1st stage depending on FSRU storage capacity availability, 2nd stage 1 x 150,000.00, 3rd stage 2 x 150,000.00, 4th stage 2
x 150,000.00
Ship Size (m3)
265,000
75,000.00 – 265,000.00 (Jetty construction and sea depth will enable Q Max LNG carriers to bearth at the site. The size of
the carriers that are going to berth alongside to the FSRU will depend on the storage and regasification capabilities of the
FSRU)
Schedule
Start Date
End Date
Pre-Feasibility
01/2013
Feasibility
07/2012
01/2014
FEED
06/2015
12/2015
Market Test
10/2015
Permitting
Supply Contracts
FID
Construction
Commissioning
2018
2018
NDP and PCI Information
Part of NDP
Yes (Desetogodišnji plan razvoja
plinskog...)
NDP Number
6.5.1.
Currently PCI
Yes (6.5.1.)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Not Applicable
Considered Tariff Regime
Not Applicable
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 280 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
89