General Information

Promoter

LNG Hrvatska d.o.o. za

poslovanje ukapljenim

prirodnim plinom

Operator

LNG Hrvatska d.o.o.

Host Country

Croatia

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

HEP d.d.

50%

Plinacro d.o.o.

50%

Technical Information (LNG)

LNG Facility

The import terminal for

the liquefied natural gas

(LNG) on the Island of Krk

Expected Volume (bcm/y)

4

1st stage - 1-4 bcm/y (According to FSRU ship and pepeline availability), 2nd stage - 3,5 bcm/y, 3rd stage - 5bcm/y, 4th

stage - 8.75 bcm/y

Storage Capacity (m3)

300,000

1st stage depending on FSRU storage capacity availability, 2nd stage 1 x 150,000.00, 3rd stage 2 x 150,000.00, 4th stage 2

x 150,000.00

Ship Size (m3)

265,000

75,000.00 – 265,000.00 (Jetty construction and sea depth will enable Q Max LNG carriers to bearth at the site. The size of

the carriers that are going to berth alongside to the FSRU will depend on the storage and regasification capabilities of the

FSRU)

Schedule

Start Date

End Date

Pre-Feasibility

01/2013

Feasibility

07/2012

01/2014

FEED

06/2015

12/2015

Market Test

10/2015

Permitting

Supply Contracts

FID

Construction

Commissioning

2018

2018

NDP and PCI Information

Part of NDP

Yes (Desetogodišnji plan razvoja

plinskog...)

NDP Number

6.5.1.

Currently PCI

Yes (6.5.1.)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Not Applicable

Considered Tariff Regime

Not Applicable

Applied for Exemption

No

Exemption Granted

No

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM