Gas Regional Investment Plan of the South Region 2017

Image courtesy of Reganosa

7.2.2 N-1 INFRASTRUCTURE ASSESSMENT

(FROM TYNDP 2017 ESW-CBA)

ENTSOG includes the N-1 indicator in the TYNDP assessment: this indicator derives

from Regulation (EC) 994/2010. It aims at identifying which countries are not able

to satisfy/meet its peak demand (1 in 20) without the larger infrastructure of the

country.

N-1 (ESW-CBA) indicator shows security of supply needs for countries with values

below 100%. Portugal is the only country in the South Region not fulfilling for all

scenarios the N-1 requirements.

The PCI 3

rd

Interconnection point PT-ES would mitigate the results for N-1 indicator

in Portugal for all demand scenarios as it can be seen in the figure below from 2025

for Green Revolution scenario.