Previous Page  14 / 76 Next Page
Information
Show Menu
Previous Page 14 / 76 Next Page
Page Background

12

MODERN MINING

August 2016

MINING News

Aftan plans upgrade of Tantalite Valley plant

A IM- l i s ted Kennedy Ven t u re s ha s

announced a conditional placing to raise

£2,0 million before expenses. The net pro-

ceeds of the placing will be used by African

Tantalum (Aftan), Kennedy Ventures’

investee company, to upgrade and expand

Aftan’s current plant at the Tantalite Valley

Mine (TVM) in Namibia and open up the

lepidolite orebody.

Kennedy Ventures says its operational

cashflow has been constrained since Aftan

reopened TVM and recommissioned the

existing processing plant at the end of 2015.

This is due to irregular mine grades and an

unexpectedly high proportion of fine tanta-

lite as mining moved through the orebody.

Additionally, TVM has encountered signifi-

cant amounts of lithium-bearing ores that

the existing plant is not currently configured

to recover. The work programme is designed

to address these issues as well as signifi-

cantly enhance the productivity of TVM.

Once the work programme has been

implemented, TVMwill target a throughput

of 15 000 tonnes per month (the previous

target was 10 500 tonnes) and an output

of 15 tonnes of tantalite concentrate. It is

anticipated that all the increased product

volume will be supplied to Aftan’s offtake

partner under the existing agreement.

Reporting on its activities during Q2 2016,

ASX-listed Syrah Resources says that

US$22,9 million was spent on the Balama

graphite project inMozambique, increasing

total project development expenditures

to US$47,1million as at 30 June 2016. An

additional US$60 million in development

expenditures has been committed, which

brings total actual and committed capital

expenditures to US$107 million, against a

revised capital cost estimate of US$175mil-

lion for the project.

According to Syrah, development

Balama well into the construction phase

activities at Balama continue to progress

well with the detailed engineering and

design on schedule for completion this

month (August). Major procurement activ-

ities are now complete with mechanical

equipment and structural steel deliveries

to Balama having begun. Regular visits

to key equipment and material suppliers

are being conducted to ensure that deliv-

ery dates and quality standards are being

maintained.

Notices of Award have been issued

for the major construction contract

(Structural, Mechanical and Piping (SMP))

and various operational contracts (includ-

ing mining, transport and logistics, fuel

supply and laboratory services).

Sealing of the 7 km access road is

complete and work is progressing on

the construction of the internal plant

site roads. Process plant and infrastruc-

ture concrete works are well advanced

with approximately 3 400 m

3

of concrete

poured in all major areas (ore bin, primary

crushing facility, primary mill and flotation

circuit) during the quarter.

Clearing for the construction of the

Tailings Storage Facility (TSF) is substan-

tially complete and construction of the

facility has begun.

There has been a substantial ramp

up of key personnel with approximately

830 direct staff and contractors currently

working on site. Ongoing recruitment of

qualified Mozambican nationals continues

to strengthen the team, says Syrah.

The site has now achieved over 1 mil-

lion hours worked without a Lost-Time

Injury.

The Balama project is situated in

Cabo Delgado Province in northern

Mozambique, some 200 km west of the

port town of Pemba. According to the

feasibility study on Balama, the project –

which will employ simple open-pit mining

– will have a production of over 350 kt/a.

A recent aerial view of the Balama project site (photo: Syrah Resources).