Previous Page  11 / 76 Next Page
Information
Show Menu
Previous Page 11 / 76 Next Page
Page Background

August 2016

MODERN MINING

9

MINING News

Resource base at Blanket increased and upgraded

Caledonia Mining Corporation, listed on the

TSX and AIM, has announced an increase

and upgrade to the resource base at its

49 %-owned subsidiary, the Blanket gold

mine in Zimbabwe.

Based on the diamond core drilling that

has been done at depth below the Blanket

section over the past half year, 343 000

tonnes have been upgraded from the

inferred to the indicated resource category

and an additional 1,28 Mt of new inventory

has been added to inferred resources.

This upgraded indicated resource

of 343 000 tonnes, combined with the

resources upgraded during 2015, have

increased the quantum of reserves and

indicated resources that may be used in the

life of mine plan from the 2,93 Mt used for

the Technical Report prepared by Minxcon

in December 2014 to 4,89 Mt currently. This

represents an increase of 67 % in terms of

mineable tonnes and hence in the life of the

mine.

Commenting on the resource upgrade,

Steve Curtis, Caledonia’s President and CEO,

said: “This upgrade reflects the ongoing

focus on resource development at Blanket

mine. It should be noted that the upgrades

are only in the Blanket section of the mine

and that further resource upgrades in the

AR South, AR Main and Eroica sections will

be released in the second half of the year.

Cat 6030 300T shovel and 10 Cat 777s, all

new machines, were delivered during the

quarter. In Q3 an additional 10 new 777s

and three new drill rigs are expected,

which – says Asanko – will go a long way

towards improving net asset utilisation,

increasing efficiencies and lowering costs.

The processing plant processed 702 318

tonnes of ore at an average grade of

1,69 g/t gold during the quarter. Recovery

of gold was in line with expectations with

higher recoveries achieved in the latter half

of the quarter once the oxygen plant was

fully operational. The average gold recov-

ery for the quarter was 92 %.

During the quarter a number of opera-

tional improvements were implemented

in the processing plant including mechan-

ical changes to the materials handling and

crushing circuits, ball mill and SAG mill

gear changes and other de-bottlenecking

work that resulted in higher than normal

planned mechanical downtime in the pro-

cessing plant. The goal of the work was

to optimise the inherent additional mill

capacity and operate at 275 000 tonnes

per month, or about 10 % above design

rates on a continuous basis. With the bulk

of the changes completed by early June,

the processing plant treated 265 000 t

during the month and is now operat-

ing at the levels anticipated from these

improvements.

Commenting on the quarter’s results,

Peter Breese, Asanko’s President and CEO,

said: “The Asanko Gold Mine delivered a

strong quarter; commercial production

was achieved a quarter ahead of sched-

ule, gold production of 36 337 ounces

was in-line with our guidance and ramp-

up to steady-state production levels was

reached within six months of starting the

new production plant.”

Updating on the status of its Sissingué

gold project in Côte d’Ivoire in its latest

quarterly report (for the period ending

30 June), Australia’s Perseus Mining says

that post the end of the quarter and fol-

lowing the successful raising of equity

finance, execution plans for the full-scale

development of Sissingué were activated.

At a total development cost to com-

pletion of US$100 million, Sissingué is

currently forecast to produce 385 000

ounces of gold at an all-in site cost of

US$632/ounce over a 5,25-year period

from first gold production to generate an

ungeared after-tax IRR of 27 % at an aver-

age gold price of US$1 200/ounce.

Perseus says negotiations with a

highly regarded Australian contrac-

tor (Lycopodium) are well advanced on

finalising the EPC contract, accounting

Perseus Mining expects late-2017

start-up for Sissingué gold project

for approximately 50 % of the estimated

construction scope. The execution of

the EPC contract is currently scheduled

for this month (August) and, given that

all required licensing, permitting and

landowner compensation has been com-

pleted, re-commencement of site works is

expected to occur in the later stages of the

September 2016 quarter.

The full scale development of Sissingué

is intended to be financed through a mix of

equity finance (US$40 million) and project

debt finance (US$60 million).

Perseus says that given the quality of the

project planning and the assembled proj-

ect management team, construction and

commissioning of Sissingué is expected to

progress reasonably quickly with first pro-

duction of gold now scheduled to occur in

the December 2017 quarter.