Previous Page  7 / 76 Next Page
Information
Show Menu
Previous Page 7 / 76 Next Page
Page Background

August 2016

MODERN MINING

5

MINING News

Reporting on Q4 2016 (to 30 June 2016),

Australia’s Kimberley Diamonds Ltd (KDL)

says that this was the first period in which

processing operations were undertaken at

its newly recommissioned Lerala diamond

mine in Botswana. During the quarter,

70 589 tonnes of ore were processed, with

10 564,11 carats recovered.

The first sale of diamonds from Lerala

was undertaken on 28 June 2016. A small

parcel of diamonds which was sourced

predominantly fromhistoric pre-2016 ROM

stockpiles was sent to Antwerp for auction.

The diamonds were sold at an average

price of US$98 per carat, with 1 110,18 car-

ats sold for total revenue of US$108 650.

The Lerala mine comprises a cluster

of five diamond-bearing kimberlite vol-

canic pipes, designated K2 to K6, and a

processing plant with a nominal capacity

of 200 t/h. The mine was opened in 2008

but was subsequently placed on care and

maintenance.

Following its acquisition of Lerala

in 2014 from Mantle Diamonds, KDL’s

Botswana subsidiary, Lerala Diamond

Mi ne s L imi ted ( Le ra l a ) , engaged

Consulmet to redesign sections of the

processing plant to facilitate improved dia-

mond recovery and throughput reliability.

Open-pit mining by the mining con-

tractor, Basil Read Botswana, began in

early April 2016 in the K3 kimberlite pipe.

During the quarter, Basil Read hauled

44 000 tonnes of stockpiled ore to the ROM

pad, mined and hauled 191 000 tonnes of

ore to the ROM pad and hauled 148 000

tonnes of low grade ore to the low grade

stockpile area.

According to Kimberley Diamonds,

mining operations have proved more than

capable of sustaining a consistent feed

Garnet separation plant commissioned

ASX-listed Mineral Commodities Ltd (MRC)

reports that its South African subsidiary,

Minerals Sands Resources (SA) Pty Ltd

(MSR), has completed the installation and

commissioning of the Garnet Separation

Plant (GSP) at its Torminmineral sands mine,

located on South Africa’s west coast 400 km

north of Cape Town.

The GSP has been installed at the front

of the existing Secondary Concentrate Plant

(SCP). It is expected to increase the non-mag-

netic zircon/rutile feed grade to the SCP by

removing the garnet fraction from the Heavy

Minerals Concentrate prior to the SCP. This, in

turn, will allow a higher grade non-magnetic

concentrate tobe fed to the existingmagnetic

circuit, thereby increasing overall final zircon/

rutile concentrate production.

Lifting Solutions That Work.

TorreLifting_657_adv_ConstructionWorld_180x55.indd 1

2016/05/20 2:09 PM

to the processing plant as it continues to

ramp up production.

Commissioning of the processing plant

commenced early in the quarter, and pro-

duction began immediately thereafter.

However, the ramp up of the plant has

Botswana’s Lerala diamond mine back in business

Kimberlite ore from the primary crusher at Lerala being fed into the new primary scrubber (photo:

Kimberley Diamonds).

been slower than anticipated as a number

of constraints to the process flow and effi-

ciency of the plant have been identified.

These are being systematically rectified

and this work will continue into the first

quarter of 2017.