Ten-Year Network Development Plan 2017 Main Report

Image courtesy of GAZ-SYSTEM

4.5.6 ANALYSIS OF PROJECTS SCHEDULE

Figure 4.10 and figure 4.11 show the distribution of submitted projects according to

the expected commissioning year, also in an aggregated way.

The analysis of project submissions shows:

\\

An average of 10 months between the planned FID and the expected start of

construction

\\

An average of 2 years and 2 months between the expected dates of start of

construction and commissioning

The way FID is taken by each promoter may differ. Some may take FID after the

granting of permits and some, before initiating the permitting procedure. Those per-

mitting procedures often make out the longest phase of the whole project schedule

which then often lasts more than 5 years. Moreover, the analysis is not necessarily

indicative of the project lead time for any future projects as there are, among the pro-

jects, some small and some very complex ones.

ENTSOG has analysed the advancement of projects between TYNDP 2015 and

TYNDP 2017. Out of the 234 projects included in TYNDP 2017, 175 were already

part of TYNDP 2015 (FID and non-FID), from which 137 have reported an expect-

ed commissioning year in both editions.