Ten-Year Network Development Plan 2017 Main Report
7
10
83
FID in TYNDP 2017
but not in TYNDP 2015
non-FID both in
TYNDP 2015 and TYNDP 2017
FID from TYNDP 2015
%
Figure 4.12:
Status in TYNDP 2017 for the projects submitted to both TYNDPs 2015 and 2017
42
58
%
Projects
in delay
Projects
not in delay
54
39
7
1–2 years
3–5 years
> 5 years
%
Figure 4.13:
Share of common projects in TYNDP 2015 and TYNDP 2017 by commissioning status
Figure 4.12 illustrates the status of those common projects according to TYNDP 2015
submission.
The charts above illustrate the share of those projects for which a delay has been
reported regarding their expected commissioning date and the length of this delay.
Among the projects without delay, 8 projects have been submitted with an earlier
commissioning date
More than half of the projects already submitted in TYNDP 2015 have reported
experiencing delays since the last edition. Listed below are the main reasons for
delays indicated by project promoters:
\\
worsened and uncertain market conditions
\\
delays in permitting/authorisations from competent authorities
\\
lack of coordination between hosting countries/political uncertainties
\\
delays in contract award procedure
\\
lack of funds/financing
\\
delay following findings from concluded pre-feasibility study