TRANSMISSION PROJECTS
Project Promoter
Name
TYNDP Code
FID Status
Commissioning
GRTgaz Deutschland GmbH
CS Rothenstadt
TRA-F-337
FID
2018
West to East operation of the IP Waidhaus
TRA-F-753
FID
2018
CS Rimpar
TRA-N-755
Non-FID (L. Adv.)
2023
GRTgaz, GRDF and Storengy
Adaptation L- gas - H-gas
TRA-N-429
Non-FID (Adv.)
2018
Natural Gas Submarine
Interconnector Greece–Italy
Poseidon S.A
Poseidon Pipeline
TRA-N-010
Non-FID (Adv.)
2020
NEL Gastransport,
Fluxys Deutschland,
Gasunie Deutschland
Extension Receiving Terminal Greifswald
TRA-F-768
FID
2017
Nord Stream 2 AG
Nord Stream 2
TRA-F-937
FID
2019
ONTRAS Gastransport GmbH
Upgrade IP Deutschneudorf and Lasow
TRA-N-814
Non-FID (Adv.)
2016
Open Grid Europe GmbH
Pipeline project “Schwandorf-Finsing”
TRA-F-343
FID
2018
Compressor station “Herbstein”
TRA-F-344
FID
2018
Compressor station “Werne”
TRA-F-345
FID
2018
ZEELINK
TRA-N-329
Non-FID (L. Adv.)
2021
Compressor station “Legden”
TRA-N-825
Non-FID (L. Adv.)
2023
Snam Rete Gas S.p.A.
Support to the North West market and bidirectional
cross-border flows
TRA-F-214
FID
2018
Development for new import from the South
(Adriatica Line)
TRA-N-007
Non-FID (L. Adv.)
2023
Interconnection with Slovenia
TRA-N-354
Non-FID (L. Adv.)
2023
Import developments from North-East
TRA-N-008
Non-FID (L. Adv.)
2034 *
Additional Southern developments
TRA-N-009
Non-FID (L. Adv.)
2034 *
Società Gasdotti Italia
LARINO - RECANATI Adriatic coast backbone
TRA-N-974
Non-FID (Adv.)
2022
Sardinia Gas Transportation Network
TRA-N-975
Non-FID (L. Adv.)
2031
TIGF
South Transit East Pyrenees (STEP) – TIGF
TRA-N-252
Non-FID (Adv.)
2022
TIGF – GRTgaz
Gascogne Midi
TRA-F-331
FID
2018
Trans Adriatic Pipeline AG
Trans Adriatic Pipeline
TRA-F-051
FID
2019
*assumed by ENTSOG for TYNDP modelling purposes
Table 2.1:
List of transmission projects [Adv.: advanced; L. Adv.: less-advanced]
(Source: ENTSOG data collection for TYNDP 2017 based on information submitted by TSOs and other project promoters)