Table of Contents Table of Contents
Previous Page  60 / 81 Next Page
Information
Show Menu
Previous Page 60 / 81 Next Page
Page Background

Local Fuel plc - Shoreham Oil Terminal

Safety Instrument System Functional Safety Assessment Stage 5

P & I Design Ltd

DOCUMENT NO: LF364100_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 15.06.2015

Tel: + 44 (0)1642 617444

PAGE 11 OF 32

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

change over be required until the SIL rated actuator is returned to service. This should produce

a MTTR in accordance with the SIL verification of within 24 hours.

b). Current company strategy is diversity in the Terminal and as the quantities of gasoline

have reduced the extra storage capacity will be utilised for Marine Gas oil because recent

legislation has increased the demand for MGO in the location.

4.6

Hazards Which May Be Affected By The Modification

No change in the hazard perceived.

a). The Rotork actuator should perform identically to the existing installed device. However,

there may be subtle differences within the actuators firmware and as such the complete system

is to be proof tested following completion of the installation.

The sensors and logic solver are as original for Tanks 1, 2, 3 & 4 gasoline tanks.

Distillate tanks 5, 6, 7, 8, 9, 10, 11, 18. 18A, 21 & 22 utilise RF technology sensors but are

alarm only.

b). The change of Tank duty will reduce the terminals current capacity for the storage of

gasoline from four to two tanks. This was addressed in the LOPA report LF364002_RPT.

4.7

The Impact On Functional Safety

a). As this is a change of actuator it is essential that it performs as specified. Checks must be

completed to ensure that systematic failures are not induced through the design phase, and

manufacturing phases, including:

o

Ensure sufficient oversizing and torque to close against ships pumps

o

Ensure slow closing not to induce pressure surge issues in import line

o

Confirm failures mode operation including loss of power

b). No impact on functional safety is perceived from the reduction in gasoline storage.

4.8

Approvals For The Modification and Competencies

For the modification, Local Fuel MOC’s will be completed and this FSA Stage 5 will be

conducted to ensure compliance to functional safety and to BS EN 61511 lifecycle.

4.9

Timescale and Timelines

a). At the FSA meeting it was advised that the Rotork is on a long delivery. However, design

has commenced with the Safety Requirement Specification having been updated.

The documentation has been revised with the references to Chevron/Valero being removed

and creating new issue drawings for Local Fuel plc. These drawings at Revision A will be

reviewed by this FSA. It may become necessary to revise them further for the modifications.