Local Fuel plc - Shoreham Oil Terminal

Safety Instrument System Functional Safety Assessment Stage 5

P & I Design Ltd

DOCUMENT NO: LF364100_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 15.06.2015

Tel: + 44 (0)1642 617444

PAGE 12 OF 32

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

4.10 Verification Process To Ensure Proper Implementation

The design is to be verified by the designer in accordance with the quality and management

of functional safety policies and in accordance with BS EN 61511. At the design stage testing

documentation is to be produced the purpose of which is to provide a series of testing

procedures which will ensure that the probability of failure on demand figure of the installed

system is maintained through the operating life of the SIS. Where known, dangerous

undetected failures should be identified and a method of detecting for these included within

the testing regime.

In addition necessary FAT and SAT are to be conducted to ensure the installed system

performs in the required manner.

All testing documentation to be reviewed as part of this FSA on completion of the

modification.

Local Fuel plc will also utilise their documents LF363003_RPT – Policy & Lifecycle

Activities and LF363004_RPT – SIS Safety Plan for Management of Functional safety

purposes.

4.11 SIS Lifecycle Requirements Of The Modification

As stated previously all lifecycle documentation is being updated and as such is to be reviewed

as part of this FSA.

4.12 Documentation That Will Require Updating:

Layer of Protection Analysis – depending on outcome of Action 1.

Safety Requirement Specification

System Verification Document

Loop Drawings

Cable & Wiring Drawings

Testing Documentation

Management of Functional Safety Document

4.13 Operating Manuals And Documentation

All design documentation is to be re-issued together with manufacturers maintenance

manuals. Local Fuel to develop operator manuals or other suitable guidelines for operation

and actions to take in the result of SIS activation.

Action 2: