Edition 47 9-53
Material Handlers
9
Lifting Capacities
●
MH3024
(Grenoble Sourced)
Lift Capacities
All values are in lb, bucket cylinder and linkage installed, hydraulic cab riser, work tool: none, with counterweight (9040 lb), heavy lift on.
Load point height
Load over front
Load over rear
Load over side
Load at maximum reach (sticknose/bucket pin)
Undercarriage
Boom
Stick
MH or Standard
One-Piece
9'6"
Undercarriage configuration
10 ft
15 ft
20 ft
25 ft
ft
25 ft
MH – stabilizers up – solid tires
*6900
*6900
*6900
21.13
MH – stabilizers down – solid tires
*6900
*6900
*6900
Lower (std UC) – f. stabilizer & r. dozer up
*6900
*6900
*6900
Lower (std UC) – f. stabilizer & r. dozer down
*6900
*6900
*6900
Lower (std UC) – f. dozer & r. stabilizer up
*6900
*6900
*6900
Lower (std UC) – f. dozer & r. stabilizer down
*6900
*6900
*6900
Lower (std UC) – 2 sets stabilizersup
*6900
*6900
*6900
Lower (std UC) – 2 sets stabilizersdown
*6900
*6900
*6900
20 ft
MH – stabilizers up – solid tires
*6100
*6100
*6100
24.93
MH – stabilizers down – solid tires
*6100
*6100
*6100
Lower (std UC) – f. stabilizer & r. dozer up
*6100
*6100
*6100
Lower (std UC) – f. stabilizer & r. dozer down
*6100
*6100
*6100
Lower (std UC) – f. dozer & r. stabilizer up
*6100
*6100
*6100
Lower (std UC) – f. dozer & r. stabilizer down
*6100
*6100
*6100
Lower (std UC) – 2 sets stabilizersup
*6100
*6100
*6100
Lower (std UC) – 2 sets stabilizersdown
*6100
*6100
*6100
15 ft
MH – stabilizers up – solid tires
12,500 12,500
9300
8800
8800
6500
*5900
*5900
5500
27.26
MH – stabilizers down – solid tires
*14,300 *14,300 *14,300 *12,800 *12,800 *12,800
*5900
*5900
*5900
Lower (std UC) – f. stabilizer & r. dozer up
12,300 11,600
8900
8500
8100
6200
*5900
*5900
5200
Lower (std UC) – f. stabilizer & r. dozer down
*14,300 *14,300 13,800 *12,800 *12,800
9600
*5900
*5900
*5900
Lower (std UC) – f. dozer & r. stabilizer up
12,700 11,200
8900
8900
7800
6200
*5900
*5900
5200
Lower (std UC) – f. dozer & r. stabilizer down
*14,300 *14,300 14,200 *12,800 *12,800
9800
*5900
*5900
*5900
Lower (std UC) – 2 sets stabilizersup
12,600 11,600
9000
8800
8100
6200
*5900
*5900
5300
Lower (std UC) – 2 sets stabilizersdown
*14,300 *14,300 *14,300 *12,800 *12,800 11,700
*5900
*5900
*5900
10 ft
MH – stabilizers up – solid tires
18,400 18,400 13,300 12,000 12,000
8800
8500
8500
6300
*5900
*5900
5000
28.51
MH – stabilizers down – solid tires
*21,200 *21,200 *21,200 *16,000 *16,000 *16,000 *13,500 *13,500 *13,500
*5900
*5900
*5900
Lower (std UC) – f. stabilizer & r. dozer up
18,200 17,000 12,700 11,700 11,100
8400
8300
7900
5900
*5900
*5900
4700
Lower (std UC) – f. stabilizer & r. dozer down
*21,200 *21,200 20,600 *16,000 *16,000 13,200 *13,500 *13,500
9300
*5900
*5900
*5900
Lower (std UC) – f. dozer & r. stabilizer up
18,800 16,400 12,700 12,100 10,700
8400
8600
7600
5900
*5900
*5900
4700
Lower (std UC) – f. dozer & r. stabilizer down
*21,200 *21,200 *21,200 *16,000 *16,000 13,600 *13,500 *13,500
9600
*5900
*5900
*5900
Lower (std UC) – 2 sets stabilizersup
18,700 16,900 12,800 12,000 11,000
8500
8500
7800
6000
*5900
*5900
4800
Lower (std UC) – 2 sets stabilizersdown
*21,200 *21,200 *21,200 *16,000 *16,000 *16,000 *13,500 *13,500 11,500
*5900
*5900
*5900
5 ft
MH – stabilizers up – solid tires
17,200 17,200 12,200 11,400 11,400
8300
8200
8200
6000
*6100
*6100
4800
28.77
MH – stabilizers down – solid tires
*24,600 *24,600 *24,600 *17,700 *17,700 *17,700 *14,200 *14,200 13,400
*6100
*6100
*6100
Lower (std UC) – f. stabilizer & r. dozer up
16,900 15,800 11,600 11,100 10,500
7800
8000
7600
5700
*6100
*6100
4500
Lower (std UC) – f. stabilizer & r. dozer down
*24,600 *24,600 19,300 *17,700 *17,700 12,600 *14,200 *14,200
9100
*6100
*6100
*6100
Lower (std UC) – f. dozer & r. stabilizer up
17,600 15,200 11,600 11,500 10,100
7800
8300
7300
5700
*6100
5900
4500
Lower (std UC) – f. dozer & r. stabilizer down
*24,600 *24,600 20,000 *17,700 *17,700 12,900 *14,200 13,500
9300
*6100
*6100
*6100
Lower (std UC) – 2 sets stabilizersup
17,400 15,700 11,700 11,500 10,400
7900
8300
7600
5700
*6100
6100
4600
Lower (std UC) – 2 sets stabilizersdown
*24,600 *24,600 *24,600 *17,700 *17,700 15,600 *14,200 14,000 11,200
*6100
*6100
*6100
0 ft
MH – stabilizers up – solid tires
16,500 16,500 11,600 11,000 11,000
7900
8000
8000
5800
*6700
*6700
4900
28.15
MH – stabilizers down – solid tires
*25,700 *25,700 *25,700 *18,500 *18,500 18,500 *14,400 *14,400 13,200
*6700
*6700
*6700
Lower (std UC) – f. stabilizer & r. dozer up
16,300 15,100 11,000 10,700 10,100
7400
7800
7400
5500
6600
6300
4600
Lower (std UC) – f. stabilizer & r. dozer down
*25,700 *25,700 18,600 *18,500 *18,500 12,100 *14,400 *14,400
8800
*6700
*6700
*6700
Lower (std UC) – f. dozer & r. stabilizer up
16,900 14,500 11,000 11,100
9700
7400
8100
7100
5500
*6700
6000
4600
Lower (std UC) – f. dozer & r. stabilizer down
*25,700 *25,700 19,300 *18,500 *18,500 12,500 *14,400 13,300
9100
*6700
*6700
*6700
Lower (std UC) – 2 sets stabilizersup
16,800 15,000 11,100 11,000 10,000
7500
8000
7300
5500
*6700
6200
4700
Lower (std UC) – 2 sets stabilizersdown
*25,700 *25,700 23,900 *18,500 *18,500 15,200 *14,400 13,700 10,900
*6700
*6700
*6700
–5 ft
MH – stabilizers up – solid tires
*21,000 *21,000 *21,000 16,400 16,400 11,400 10,800 10,800
7700
7900
7900
5700
7400
7400
5300
26.51
MH – stabilizers down – solid tires
*21,000 *21,000 *21,000 *24,400 *24,400 *24,400 *18,000 *18,000 *18,000 *13,500 *13,500 13,100
*7700
*7700
*7700
Lower (std UC) – f. stabilizer & r. dozer up
*21,000 *21,000 20,000 16,100 14,900 10,800 10,500
9900
7300
7700
7300
5400
7100
6800
5000
Lower (std UC) – f. stabilizer & r. dozer down
*21,000 *21,000 *21,000 *24,400 *24,400 18,400 *18,000 *18,000 12,000 *13,500 *13,500
8700
*7700
*7700
*7700
Lower (std UC) – f. dozer & r. stabilizer up
*21,000 *21,000 20,000 16,700 14,300 10,800 10,900
9500
7300
8000
7000
5400
7400
6500
5000
Lower (std UC) – f. dozer & r. stabilizer down
*21,000 *21,000 *21,000 *24,400 *24,400 19,100 *18,000 *18,000 12,300 *13,500 13,200
9000
*7700
*7700
*7700
Lower (std UC) – 2 sets stabilizersup
*21,000 *21,000 20,300 16,600 14,800 10,900 10,800
9800
7400
8000
7300
5500
7400
6700
5100
Lower (std UC) – 2 sets stabilizersdown
*21,000 *21,000 *21,000 *24,400 *24,400 23,700 *18,000 *18,000 15,000 *13,500 *13,500 10,800
*7700
*7700
*7700
–10 ft
MH – stabilizers up – solid tires
*28,600 *28,600 21,500 16,500 16,500 11,500 10,800 10,800
7700
8700
8700
6300
23.69
MH – stabilizers down – solid tires
*28,600 *28,600 *28,600 *21,100 *21,100 *21,100 *15,600 *15,600 *15,600
*9700
*9700
*9700
Lower (std UC) – f. stabilizer & r. dozer up
*28,600 *28,600 20,400 16,200 15,100 10,900 10,600 10,000
7300
8400
8000
5900
Lower (std UC) – f. stabilizer & r. dozer down
*28,600 *28,600 *28,600 *21,100 *21,100 18,500 *15,600 *15,600 12,000
*9700
*9700
9600
Lower (std UC) – f. dozer & r. stabilizer up
*28,600 28,300 20,400 16,800 14,500 10,900 11,000
9600
7300
8800
7700
5900
Lower (std UC) – f. dozer & r. stabilizer down
*28,600 *28,600 *28,600 *21,100 *21,100 19,200 *15,600 *15,600 12,400
*9700
*9700
*9700
Lower (std UC) – 2 sets stabilizersup
*28,600 *28,600 20,600 16,700 15,000 11,100 10,900
9900
7400
8700
8000
6000
Lower (std UC) – 2 sets stabilizersdown
*28,600 *28,600 *28,600 *21,100 *21,100 *21,100 *15,600 *15,600 15,000
*9700
*9700
*9700
–15 ft
MH – stabilizers up – solid tires
*14,500 *14,500 12,000
MH – stabilizers down – solid tires
*14,500 *14,500 *14,500
Lower (std UC) – f. stabilizer & r. dozer up
*14,500 *14,500 11,400
Lower (std UC) – f. stabilizer & r. dozer down
*14,500 *14,500 *14,500
Lower (std UC) – f. dozer & r. stabilizer up
*14,500 *14,500 11,400
Lower (std UC) – f. dozer & r. stabilizer down
*14,500 *14,500 *14,500
Lower (std UC) – 2 sets stabilizersup
*14,500 *14,500 11,500
Lower (std UC) – 2 sets stabilizersdown
*14,500 *14,500 *14,500
*Limited by hydraulic rather than tipping load.
Lift capacity ratings are based on ISO 10567:2007, they do not exceed 87% of hydraulic lifting capacity or 75% of tipping load. The load point is the center line of the bucket pivot mounting pin on the stick. The oscillating
axle must be locked. Lifting capacities are based on the machine standing on a firm uniform supporting surface. For lifting capacity including bucket and/or quick coupler, the respective weight has to be subtracted from
above values. The use of a work tool attachment point to handle/lift objects, could affect the machine lift performance.
Always refer to the appropriate Operation and Maintenance Manual for specific product information.