Edition 47 9-55

Material Handlers

9

Lifting Capacities

MH3024

(Grenoble Sourced)

Lift Capacities

All values are in lb, bucket cylinder and linkage installed, hydraulic cab riser, work tool: none, with counterweight (11,470 lb), heavy lift on.

Load point height

Load over front

Load over rear

Load over side

Load at maximum reach (sticknose/bucket pin)

Undercarriage

Boom

Stick

MH or Standard

One-Piece

9'6"

Undercarriage configuration

10 ft

15 ft

20 ft

25 ft

ft

25 ft

MH – stabilizers up – solid tires

*6900

*6900

*6900

21.13

MH – stabilizers down – solid tires

*6900

*6900

*6900

Lower (std UC) – f. stabilizer & r. dozer up

*6900

*6900

*6900

Lower (std UC) – f. stabilizer & r. dozer down

*6900

*6900

*6900

Lower (std UC) – f. dozer & r. stabilizer up

*6900

*6900

*6900

Lower (std UC) – f. dozer & r. stabilizer down

*6900

*6900

*6900

Lower (std UC) – 2 sets stabilizersup

*6900

*6900

*6900

Lower (std UC) – 2 sets stabilizersdown

*6900

*6900

*6900

20 ft

MH – stabilizers up – solid tires

*6100

*6100

*6100

24.93

MH – stabilizers down – solid tires

*6100

*6100

*6100

Lower (std UC) – f. stabilizer & r. dozer up

*6100

*6100

*6100

Lower (std UC) – f. stabilizer & r. dozer down

*6100

*6100

*6100

Lower (std UC) – f. dozer & r. stabilizer up

*6100

*6100

*6100

Lower (std UC) – f. dozer & r. stabilizer down

*6100

*6100

*6100

Lower (std UC) – 2 sets stabilizersup

*6100

*6100

*6100

Lower (std UC) – 2 sets stabilizersdown

*6100

*6100

*6100

15 ft

MH – stabilizers up – solid tires

14,000 14,000 10,600

9900

9900

7500

*5900

*5900

*5900

27.26

MH – stabilizers down – solid tires

*14,300 *14,300 *14,300 *12,800 *12,800 *12,800

*5900

*5900

*5900

Lower (std UC) – f. stabilizer & r. dozer up

13,800 13,100 10,200

9700

9200

7100

*5900

*5900

*5900

Lower (std UC) – f. stabilizer & r. dozer down

*14,300 *14,300 *14,300 *12,800 *12,800 10,800

*5900

*5900

*5900

Lower (std UC) – f. dozer & r. stabilizer up

14,200 12,700 10,200 10,000

8900

7100

*5900

*5900

*5900

Lower (std UC) – f. dozer & r. stabilizer down

*14,300 *14,300 *14,300 *12,800 *12,800 11,100

*5900

*5900

*5900

Lower (std UC) – 2 sets stabilizersup

14,200 13,000 10,300 10,000

9200

7200

*5900

*5900

*5900

Lower (std UC) – 2 sets stabilizersdown

*14,300 *14,300 *14,300 *12,800 *12,800 *12,800

*5900

*5900

*5900

10 ft

MH – stabilizers up – solid tires

20,600 20,600 15,100 13,500 13,500 10,100

9700

9700

7200

*5900

*5900

5900

28.51

MH – stabilizers down – solid tires

*21,200 *21,200 *21,200 *16,000 *16,000 *16,000 *13,500 *13,500 *13,500

*5900

*5900

*5900

Lower (std UC) – f. stabilizer & r. dozer up

20,500 19,100 14,500 13,200 12,500

9700

9400

9000

6900

*5900

*5900

5600

Lower (std UC) – f. stabilizer & r. dozer down

*21,200 *21,200 *21,200 *16,000 *16,000 14,800 *13,500 *13,500 10,500

*5900

*5900

*5900

Lower (std UC) – f. dozer & r. stabilizer up

21,100 18,500 14,500 13,700 12,100

9700

9800

8700

6900

*5900

*5900

5600

Lower (std UC) – f. dozer & r. stabilizer down

*21,200 *21,200 *21,200 *16,000 *16,000 15,200 *13,500 *13,500 10,800

*5900

*5900

*5900

Lower (std UC) – 2 sets stabilizersup

21,000 19,000 14,700 13,600 12,400

9800

9700

8900

7000

*5900

*5900

5600

Lower (std UC) – 2 sets stabilizersdown

*21,200 *21,200 *21,200 *16,000 *16,000 *16,000 *13,500 *13,500 12,800

*5900

*5900

*5900

5 ft

MH – stabilizers up – solid tires

19,400 19,400 14,000 12,900 12,900

9500

9400

9400

7000

*6100

*6100

5600

28.77

MH – stabilizers down – solid tires

*24,600 *24,600 *24,600 *17,700 *17,700 *17,700 *14,200 *14,200 *14,200

*6100

*6100

*6100

Lower (std UC) – f. stabilizer & r. dozer up

19,200 17,900 13,400 12,600 11,900

9100

9200

8700

6600

*6100

*6100

5400

Lower (std UC) – f. stabilizer & r. dozer down

*24,600 *24,600 21,700 *17,700 *17,700 14,200 *14,200 *14,200 10,300

*6100

*6100

*6100

Lower (std UC) – f. dozer & r. stabilizer up

19,800 17,300 13,400 13,100 11,500

9100

9500

8400

6600

*6100

*6100

5400

Lower (std UC) – f. dozer & r. stabilizer down

*24,600 *24,600 22,400 *17,700 *17,700 14,600 *14,200 *14,200 10,500

*6100

*6100

*6100

Lower (std UC) – 2 sets stabilizersup

19,700 17,800 13,500 13,000 11,900

9200

9400

8600

6700

*6100

*6100

5400

Lower (std UC) – 2 sets stabilizersdown

*24,600 *24,600 *24,600 *17,700 *17,700 17,400 *14,200 *14,200 12,500

*6100

*6100

*6100

0 ft

MH – stabilizers up – solid tires

18,700 18,700 13,400 12,500 12,500

9100

9100

9100

6800

*6700

*6700

5700

28.15

MH – stabilizers down – solid tires

*25,700 *25,700 *25,700 *18,500 *18,500 *18,500 *14,400 *14,400 *14,400

*6700

*6700

*6700

Lower (std UC) – f. stabilizer & r. dozer up

18,500 17,200 12,800 12,200 11,500

8700

8900

8500

6400

*6700

*6700

5500

Lower (std UC) – f. stabilizer & r. dozer down

*25,700 *25,700 21,000 *18,500 *18,500 13,700 *14,400 *14,400 10,000

*6700

*6700

*6700

Lower (std UC) – f. dozer & r. stabilizer up

19,200 16,600 12,800 12,600 11,100

8700

9200

8200

6400

*6700

*6700

5500

Lower (std UC) – f. dozer & r. stabilizer down

*25,700 *25,700 21,700 *18,500 *18,500 14,100 *14,400 *14,400 10,300

*6700

*6700

*6700

Lower (std UC) – 2 sets stabilizersup

19,100 17,100 12,900 12,600 11,500

8800

9200

8400

6500

*6700

*6700

5500

Lower (std UC) – 2 sets stabilizersdown

*25,700 *25,700 *25,700 *18,500 *18,500 17,000 *14,400 *14,400 12,300

*6700

*6700

*6700

–5 ft

MH – stabilizers up – solid tires

*21,000 *21,000 *21,000 18,500 18,500 13,200 12,300 12,300

9000

9100

9100

6700

*7700

*7700

6200

26.51

MH – stabilizers down – solid tires

*21,000 *21,000 *21,000 *24,400 *24,400 *24,400 *18,000 *18,000 *18,000 *13,500 *13,500 *13,500

*7700

*7700

*7700

Lower (std UC) – f. stabilizer & r. dozer up

*21,000 *21,000 *21,000 18,300 17,000 12,600 12,000 11,300

8500

8900

8400

6400

*7700

*7700

5900

Lower (std UC) – f. stabilizer & r. dozer down

*21,000 *21,000 *21,000 *24,400 *24,400 20,800 *18,000 *18,000 13,600 *13,500 *13,500

9900

*7700

*7700

*7700

Lower (std UC) – f. dozer & r. stabilizer up

*21,000 *21,000 *21,000 19,000 16,400 12,600 12,500 10,900

8500

9200

8100

6400

*7700

7500

5900

Lower (std UC) – f. dozer & r. stabilizer down

*21,000 *21,000 *21,000 *24,400 *24,400 21,500 *18,000 *18,000 13,900 *13,500 *13,500 10,200

*7700

*7700

*7700

Lower (std UC) – 2 sets stabilizersup

*21,000 *21,000 *21,000 18,900 16,900 12,800 12,400 11,300

8600

9100

8300

6400

*7700

*7700

6000

Lower (std UC) – 2 sets stabilizersdown

*21,000 *21,000 *21,000 *24,400 *24,400 *24,400 *18,000 *18,000 16,800 *13,500 *13,500 12,200

*7700

*7700

*7700

–10 ft

MH – stabilizers up – solid tires

*28,600 *28,600 24,700 18,700 18,700 13,400 12,300 12,300

9000

*9700

*9700

7300

23.69

MH – stabilizers down – solid tires

*28,600 *28,600 *28,600 *21,100 *21,100 *21,100 *15,600 *15,600 *15,600

*9700

*9700

*9700

Lower (std UC) – f. stabilizer & r. dozer up

*28,600 *28,600 23,600 18,500 17,200 12,700 12,100 11,400

8600

9700

9200

7000

Lower (std UC) – f. stabilizer & r. dozer down

*28,600 *28,600 *28,600 *21,100 *21,100 20,900 *15,600 *15,600 13,600

*9700

*9700

*9700

Lower (std UC) – f. dozer & r. stabilizer up

*28,600 *28,600 23,600 19,100 16,600 12,700 12,500 11,000

8600

*9700

8800

7000

Lower (std UC) – f. dozer & r. stabilizer down

*28,600 *28,600 *28,600 *21,100 *21,100 *21,100 *15,600 *15,600 14,000

*9700

*9700

*9700

Lower (std UC) – 2 sets stabilizersup

*28,600 *28,600 23,900 19,000 17,100 12,900 12,400 11,300

8700

*9700

9100

7000

Lower (std UC) – 2 sets stabilizersdown

*28,600 *28,600 *28,600 *21,100 *21,100 *21,100 *15,600 *15,600 *15,600

*9700

*9700

*9700

–15 ft

MH – stabilizers up – solid tires

*14,500 *14,500 13,800

MH – stabilizers down – solid tires

*14,500 *14,500 *14,500

Lower (std UC) – f. stabilizer & r. dozer up

*14,500 *14,500 13,200

Lower (std UC) – f. stabilizer & r. dozer down

*14,500 *14,500 *14,500

Lower (std UC) – f. dozer & r. stabilizer up

*14,500 *14,500 13,200

Lower (std UC) – f. dozer & r. stabilizer down

*14,500 *14,500 *14,500

Lower (std UC) – 2 sets stabilizersup

*14,500 *14,500 13,300

Lower (std UC) – 2 sets stabilizersdown

*14,500 *14,500 *14,500

*Limited by hydraulic rather than tipping load.

Lift capacity ratings are based on ISO 10567:2007, they do not exceed 87% of hydraulic lifting capacity or 75% of tipping load. The load point is the center line of the bucket pivot mounting pin on the stick. The oscillating

axle must be locked. Lifting capacities are based on the machine standing on a firm uniform supporting surface. For lifting capacity including bucket and/or quick coupler, the respective weight has to be subtracted from

above values. The use of a work tool attachment point to handle/lift objects, could affect the machine lift performance.

Always refer to the appropriate Operation and Maintenance Manual for specific product information.