Pipeline including CS
Same project as TRA-F-059
SPONSORS
GENERAL INFORMATION
FINANCING
TEN-E Project ?
37%
In PCI list ?
63%
IGAs
–
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
TRA-F-029
RO-BG Interconnection
FID
Promoter
Transgaz
Not part of TEN-E
Public Financing
Operator
Transgaz
No
Private Financing
Web Link
None
Multilateral Financing
Applied for Exemption ?
No
Construction
2013 Q2
Total Compressor Power (MW)
# of Pipelines, nodes, CS
1
Considered Tariff Regime
Regulated
FID
2010 Q4
Total Pipeline Length (km)
+25.00
Considered TPA Regime
Regulated
End of permitting phase
2011 Q4
% Exemption in entry direction
–
Last completed Phase :
FID
Diameter (range) (mm)
DN 500
Exemption granted ?
Not relevant
Commissioning
2014 Q2
Expected Load Factor
+1.00
% Exemption in exit direction
–
Diameter (range) (inches)
20"
Print
ENTSOG TYNDP 2013-2013 - Annex A
Southern Corridor GRIP 2014–2023 Annex B |
27