ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects - page 34

Modelled Direction
Yes
entry
Yes
exit
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
Balassagyarmat
127.40
Hub Slovakia
Hub Hungary (SK-HU Interconnector)
50.90
Hub Hungary (SK-HU
Hub Slovakia
DESCRIPTION OF THE PROJECT
Hungarian section 92 km. Slovak section 18 km. PN 75 bar. Bidirectional transportation possibility.
EXPECTED BENEFITS
Security of Supply, Market integration
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
ENTSOG TYNDP 2013-2013 - Annex A
Southern Corridor GRIP 2014–2023 Annex B |
34