ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects - page 39

SPONSORS
GENERAL INFORMATION
FINANCING
TEN-E Project ?
In PCI list ?
IGAs
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
TRA-F-214
Support to the North West Market and bidirectional cross-border flows
FID
Pipeline including CS
None
Multilateral Financing
Web Link
013_2014/Ten-year-Plan/index.html
Promoter
Snam Rete Gas S.p.A.
Not part of TEN-E
Public Financing
Operator
Snam Rete Gas S.p.A.
Yes
Private Financing
Considered TPA Regime
Regulated
End of permitting phase
# of Pipelines, nodes, CS
1
Applied for Exemption ?
No
Construction
Total Compressor Power (MW)
+95.00
Considered Tariff Regime
Regulated
FID
Total Pipeline Length (km)
+80.00
% Exemption in entry direction
Last completed Phase :
FID
Diameter (range) (mm)
DN 1200
Exemption granted ?
Not relevant
Commissioning
2017 Q4
Expected Load Factor
% Exemption in exit direction
The project consists of sub projects that are in different stages of progress
Diameter (range) (inches)
48"
Print
ENTSOG TYNDP 2013-2013 - Annex A
Southern Corridor GRIP 2014–2023 Annex B |
39