ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects - page 33

SPONSORS
GENERAL INFORMATION
FINANCING
TEN-E Project ?
In PCI list ?
IGAs
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
TRA-F-148
Slovak-Hungarian interconnector (Vecsés-Szada-Balassagyarmat)
FID
Pipeline including CS
1
Multilateral Financing
Web Link
Promoter
Magyar Gaz Tranzit Zrt.
Not part of TEN-E
Public Financing
Operator
MGT Hungarian Gas Transit Ltd.
Yes
Private Financing
Considered TPA Regime
regulated
End of permitting phase
2014
# of Pipelines, nodes, CS
2
Applied for Exemption ?
No
Construction
2013
Total Compressor Power (MW)
Considered Tariff Regime
regulated
FID
Total Pipeline Length (km)
+110
% Exemption in entry direction
Last completed Phase :
FID
Diameter (range) (mm)
DN 800
Exemption granted ?
no
Commissioning
2015 Q1
Expected Load Factor
% Exemption in exit direction
Diameter (range) (inches)
32"