Local Fuel PLC – The Shoreham Oil Terminal

SIS Management of Functional Safety – Safety Plan

P & I Design Ltd

DOCUMENT NO:LP364004_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: C DATE: 27.05.15

Tel: + 44 (0)1642 617444

PAGE 21 OF 28

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

14

FUNCTIONAL SAFETY ASSESSMENT – STAGE 3

Stage 3 FSA - After the installation, pre-commissioning and final validation of the SIS has

been completed and operating and maintenance procedures have been developed.

14.1 Functional Safety Assessment Stage 3 Requirements

Lifecycle

phase in

Figure 1

Activity

10

Functional Safety Assessment Stage 3

Objectives

Inputs

Outputs

Deliverables

Responsible persons

and or organisations

To investigate and arrive at

a judgement on the

functional safety achieved

by the SIS

Planning for SIS

functional safety

assessment

SRS

Design Manual

As Built

Documentation

PFD & SIL

Verification

Calculations

Results of SIS

functional safety

assessment

Functional Safety

Assessment

Stage 3

Document

Functional Safety

Manager

FSA Chairperson

FSA Team

Functional Safety Assessment

Proposed Agenda:

The FSA will address the following as a minimum:

The recommendations and actions arising from the Stage 1 & 2 FSA have been resolved and completed;

That project design change procedures are in place and properly implemented.

The SIS is installed and pre-commissioned in accordance with the design and the SRS, any differences to be

identified and resolved;

The safety, operating, maintenance and emergency procedures pertaining to the SIS are in place;

The employee training has been completed and appropriate information about the SIS has been provided to the

maintenance and operating personnel;

Plans or strategies for implementing further FSA’s are in place;

14.2 Functional Safety Assessment Stage 3 Action History

Activity History – Terminal in Texaco/Chevron/Valero ownership

Date

Reference

Description

Roles

Persons Assigned

27.06.08 SI157001.RPT A Functional Safety

Assessment Stage 3 was

conducted for all

terminals in a joint

assessment.

Chair

FSA Team

FSA Team

D R Ransome BA CEng FInstMC – P & I Design Ltd

I Goldsworthy – Facility Engineer – Chevron Ltd

D S Regan BEng – Process Engineer – P & I Design

Ltd