Background Image
Previous Page  33 / 44 Next Page
Information
Show Menu
Previous Page 33 / 44 Next Page
Page Background

March 2015

AFRICAN FUSION

31

Each structural section is flanged at the ends so that so that the 84 m towers can

be erected onsite by bolting them together.

On the growing line, ESAB roller beds with built in manipulators are used to

support the growing section and the can to be added.

A completed tower section on one of DCD Wind Tower’s four growing line.

rotating rollers and shuffle it along and onto a roller bed

further up the line. A newcan is then loaded andwelded,

before the whole weldment is shuffled up a further

3,0 m. The welding is done using state-of-the-art ESAB

submergedarcweldingequipment, with thewhole tower

section being rotated to complete each circular seam.

“Visual and UT testing is required following each

weld, but we have alsonow introducesmagnetic particle

testing on some cans to ensure that we don’t miss any

surface cracks,” Jauka says, adding that each section

has flanges on its ends, “so the flange is the first and

last circumferential joint”.

At the top end of the growing line, completed tower

sections are lifted and placed on another set of 35 m

roller beds for testing. Following final inspection and

repair, a team of boiler makers is brought into the sec-

tion to mark off positions for internal bracketry and

fittings. Welders will then collect the relevant bracket

kit from stores and, using mostly flux-cored welding,

they weld them on.

The final operation on the fabrication side of the

line – the black section operation – is to do Easy-Laser

®

alignment and flame straightening on the flange sur-

faces. “Flange flatness must be within 2,0 mm across

the 4.5 m to 5,0 m diameter to ensure that when bolted

together onsite, the flanges seal against each other and

the bolts can be tightened without inducing stresses,”

Jauka explains. “The laser alignment system gives us a

printout highlighting twist and distortion, which is then

used to determine where flame straightening is needed

to bring the flange into tolerance,” he says.

From the top end of the line, the completed tower

section is brought back down the U-shaped facility on

a parallel path – the white section operation. It first en-

ters a wash bay for the removal of any gel, grits and oil.

Once dry, grit blasters are used to descale the surfaces

inside and out. For cathodic protection across the flange

connections of the tower sections, “we are required to

metallise an areawithin about 500mmof the flange and

all around access hatches and doorways with a 40

µ

m

layer of zinc. We therefore look for surface roughness of

between SA2 and SA3 fromour grit blasting operations,

before using the twin-wire arc spray process to deposit

the metallic layer,” he says. “Grit blasting also has to be

done under controlled humidity conditions, so we are

currently installing a humidity controller so that we will

no longer be dependent on appropriate ambient condi-

tions to complete this task.”

Following metalising, the tower section enters one

of three paint booths, PB1, PB2 or PB3. The section is

placed on a paint rotator supported and driven via the

flange rings on either side. This allows access to the full

surface for painting.

Once painted, the last stage of manufacture is to fit

the platforms, rails, ladders and internal fixtures onto

the welded bracketry. These components are also sup-

plied in kit form from Vestas. “We then move the tower

section into the yard for a final inspection. When we are

happy, we cover the ends attach the lower feet, enclose

the whole structure in tarpaulin and arrange for trans-

portation to site,” Jauka notes.

“It is currently taking us six to 10 days to complete

a top section, seven to 12 days for a middle section and up to 14

days for the bottom sections because of their heavier material

thicknesses. But we are not yet at full production. We hope to

be running all four lines in the near future, which will allow us to

complete six sections per week.

The facility was designed to produce 110 towers per year, or

330 sections. If we can persuade a few skilled people to join us

here in Port Elizabeth, we will soon be meeting our production

expectations,” he concludes.