Ten-Year Network Development Plan 2017 Main Report |

225

6.4.1.3 N-1 for ESW-CBA infrastructure assessment

For Croatia, Estonia, Greece, Lithuania and Slovenia the N-1 for ESW-CBA indicator

improves significantly, mainly thanks to new connection to LNG and additional inter-

connection capacity in between these countries and with other countries commis-

sioned around 2020. In Estonia, Greece and Slovenia the improvement is up to ex-

ceeding 100% in all scenarios.

In Finland, where the N-1 for ESW-CBA was only ensured by its limited indigenous

production in the Low infrastructure level, the connection to the Baltic States brings

significant improvement, while not still ensuring a 100% level along the whole time

horizon.

The N-1 for ESW-CBA is not improved for Ireland, Denmark and Portugal. Results

for the following modelling results: N-1 for ESW-CBA

Blue Transition

2020 Advanced

EU Green Revolution

2020 Advanced

Blue Transition

2030 Advanced

EU Green Revolution

2030 Advanced

N-1, Blue Transition and EU Green Revolution, DC, Advanced infrastructure level

0%

90%

120%

100%

>120%

Figure 6.33:

N-1 for ESW-CBA, Blue Transition and EU Green Revolution, DC, Advanced

infrastructure level