Local Fuel PLC – The Shoreham Oil Terminal

Safety Instrument System Overfill Shutdown Conditions Proof Testing Procedure LFS-SIS1

P & I Design Ltd

DOCUMENT NO: LF364012_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 20.05.15

Tel: + 44 (0)1642 617444

PAGE 13 OF 22

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

7.3

Drexelbrook Sensor As Found Physical Test Functional Testing

Physical testing of Drexelbrook sensors required minimum of every 8 years.

Refer to LF364004_SCH - LFS-SIS1 Testing Lifecycle Matrix for scheduling.

Purpose of Test

To verify the SIF operates correctly under simulated process conditions.

SIF is SENSOR ELEMENT trips & inhibits the FINAL ELEMENT(s) to the safe state as specified.

Method of activation is by physically removing the sensor element.

To verify the correct DIAGNOSTICS information.

If sensing element defective the tank could overfill if a demand is made on the overfill protection

system.

If response target time is exceeded the tank could overfill following demand.

Diagnostic information not displayed correctly could result in undetected tank overfill, system

unavailability or incorrect operational response.

If a physical test not carried out every 8 years the PDF of the system will fall outside of the defined

SIL.

Controlled Copy Documentation Required

LF364003_SCH - LFS-SIS1 Testing Matrix

Record results on LF364003_SCH Sheets 2 & 4.

Step

Method of Test

Acceptance Criteria

Pass (

)

Fail (x)

Initial

7.3.1

Review procedure with operations and

testing personnel.

All personnel familiarised with the

scope of works and responsibilities

.

Comment any issues in section 7.3.8 and

review / rectify prior to starting testing.

7.3.2

Confirm plant preparations satisfactory

prior to each period of work and

following changes in plant conditions

or operations.

Record PTW No………………………….

Conditions satisfied as detailed on PTW

and RAMS.

Comment any issues in section 7.3.8 and

review / rectify prior to starting any site

work.

7.3.3

Confirm system healthy and reset by

comparing against information on

LF364003_SCH Sheet 1

System reset as detailed on

LF364003_SCH Sheet 1.

Comment differences from SCH or if

found in tripped state in section 7.3.8.

7.3.4

Confirm all final element valves

tripped by the initiator under test are

open.

Correct FINAL ELEMENT valve

position and DIAGNOSTICS as detailed

on LF364003_SCH Sheet 2.

Comment differences from SCH in

section 7.3.8.

Drexelbrook Sensor As Found Physical Test Functional Testing Continued on page 14