June 2017
7-23
City of Morgan Hill
Water System Master Plan
BR-P2:
Construct a new 10-inch pipeline in Cochrane Road between Half Road and
approximately 1,700 feet north of Half Road.
BR-P3:
Construct a new 12-inch pipeline in Half Road between Avenida de los Padres
and approximately 450 feet south of Avenida de los Padres.
BR-P4:
Replace existing 8-inch pipeline with a new 10-inch pipeline in Mission View Drive
between Cochrane Road and 2,100 feet northwest of Cochrane Road.
BR-P5:
Construct a new 12-inch pipeline in De Paul Road between Half Road and 2,100
feet northwest of Half Road.
BR-P6:
Construct a new 12-inch pipeline in Half Road between Serene Road and Condit
Road.
7.8.2
Nob Hill Pressure Zone
This section documents pipeline improvements within the Nob Hill Pressure Zone.
NH-P1:
Construct a new 12-inch pipeline in Hale Avenue Extension between Spring
Avenue and Main Avenue.
NH-P2:
Replace existing 4-inch pipeline with a new 8-inch pipeline in Spring Avenue
between Del Monte Avenue and Monterey Road.
NH-P3:
Replace existing 10-inch pipeline with a new 16-inch pipeline in San Pedro
Avenue between Butterfield Boulevard and Railroad Avenue.
NH-P4:
Replace existing 10-inch pipeline with a new 16-inch pipeline in Railroad Avenue
between San Pedro Avenue and approximately 600 feet north of Mast Street.
NH-P5:
Replace existing 6-inch pipeline with a new 16-inch pipeline in Railroad Avenue
between S600 feet north of Mast Street and Mast Street.
NH-P6:
Construct a new 10-inch pipeline in San Pedro Avenue between Peppertree Drive
and Hill Road.
NH-P7:
Construct a new 10-inch pipeline in Hill Road between San Pedro Avenue and
Tennant Avenue.
NH-P8:
Construct a new 10-inch pipeline in Tennant Avenue between Hill Road and
Condit Road.
NH-P9:
Construct a new 10-inch pipeline in Monterey Road between John Wilson way and
Middle Avenue.
NH-P10:
Construct a new 10-inch pipeline in right of way between Monterey Road and
Olive Avenue.